Press release
By Aneel
This is an automatic translation of the press release originally published in Portuguese.
The Collegial Council of the National Electric Energy Agency – ANEEL approved this Tuesday (26/07) the Auction project N° of volt-ampere (MVA) in the transformation capacity of substations, in addition the maintenance in service of 1,123 km of transmission lines and 2,200 MW in converter stations. The auction is scheduled for December 16 at B3’s headquarters in São Paulo.
The six lots of the public notice have an investment expectation of 3.27 billion reais, with a forecast of the creation of 5,674 direct jobs. The projects, with a completion period of 42 to 60 months, will cover the states of Espírito Santo, Maranhão, Minas Gerais, Pará, Rio de Janeiro, Rio Grande do Sul, Rondônia and São Paulo.
Lots 5 and 6 are unique in that they concern the revitalization and maintenance of existing projects to extend their useful life. In the case of lot 5, the revitalization of the control and teleprotection systems of the Garabi I and II converters, in Rio Grande do Sul, aims to guarantee the continuity of the international interconnection with Argentina. Lot 6 is for the implementation of a new service at Centro Substation, São Paulo, by changing the voltage level from 230 to 345 kilovolts (kV) in an insulated busbar (GIS) and replacing transformations.
Batch |
Companies |
states) |
Duration (months) |
Objective |
1 |
– LT 230kV Governador Valadares 6 – Verona, CS, C1, with 165 km. |
MG/ES |
54 |
Service to the Northern Region of the State of Espírito Santo |
of them |
– LT 230kV Porto Velho – Abunã, CS, C3, with 188 km. |
OR |
60 |
Increased reliability in service in the state of Acre. |
3 |
– SE 500/230/69 kV Açailândia – Transformation 500/230 kV (6+1Res) x 150 MVA and transformation 230/69 kV 2×75 MVA; – SE 500/230/138 kV Santa Luzia III – Transformation 500/230 kV (6+1Res) x 150 MVA and transformation 230/138 kV 2 x 100 MVA; – SE 230/69 kV Dom Eliseu II – 2 x 75 MVA; – SE Encruzo Novo – Synchronous Compensation, “Shunt” Capacitor Bank and Bar Reactor Bank; – LV 500 kV sections between SE Santa Luzia III and LV 500 kV Açailândia – Miranda II, C1, with 1.7 and 1.0 km; – BT 230 kV Encruzo Novo – Santa Luzia III, CS, C1, with 207 km; – LT 230 kV Açailândia – Dom Eliseu II, C1 and C2, CD, with 71.5 km. |
MA/AP |
60 |
Supply to the Regions of Açailândia, Buriticupu, Vitorino Freire (MA) and Dom Eliseu (PA). |
4 |
– SE 345/138 kV Porto do Açu – (6+1R) x 50 MVA; – LV 345 kV sections between SE Porto do Açu and LV 345 kV Campos – UTE GNA I, C1, with 2 x 1.6 km; – LV 345 kV sections between SE Porto do Açu and LV 345 kV Campos – UTE GNA I, C2, with 2 x 1.6 km; |
RJ |
42 |
Service at the Porto do Açu and Santo Amaro complex in the state of Rio de Janeiro. |
5 |
– Garabi I and II facilities – 2,200 MW – continuity of the existing public transport service and revitalization of the converter control and teleprotection systems. |
LOL |
60 |
Guarantee the continuity of the international interconnection with Argentina. |
6 |
– SE 345/88-20 kV Centro – implementation of a new service at the substation with change of voltage level from 230 to 345 kV in isolated busbars (GIS) and replacement of transformations at 345/88 kV – 4×150 MVA and 345/20- 20 kV – reserve 3×150 MVA and 1×150 MVA. Assets will be transferred to the auction winner, responsible for operating existing facilities and revitalization. |
PS |
60 |
Establishment of a new service at the Centro substation to serve the São Paulo metropolitan area. |
The draft public notice and documentation relating to the six lots were reviewed by the company under public consultation No. 24/2022, which received 96 contributions from 16 participants, of which 38 were fully or partially accepted. The text approved by ANEEL will follow in the coming days for examination by the Federal Court of Auditors.
The advice is expected to be approved by the ANEEL Board in November 2022, including the adjustments suggested by the TCU. A technical clarification workshop on the main points of the event is scheduled for October 21.
To keep reading, subscribe to BNamericas to get all the information in this article and access related news and reports.